VANCOUVER, BC / ACCESSWIRE / November 7, 2019 / Skeena Resources Limited (TSX.V:SKE) (OTCQX:SKREF) ('Skeena' or the 'Company') is pleased to announce the initial Preliminary Economic Assessment ('PEA') completed by Ausenco Engineering Canada Inc. ('Ausenco'), supported by SRK Consulting (Canada), and AGP Mining Consultants, for the Eskay Creek gold-silver project ('Eskay Creek' or the 'Project') located in the Golden Triangle of British Columbia.
Eskay Creek 2019 PEA Highlights:
1. Exchange Rate (US$/C$) of 0.77
2. Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties
3. AISC includes cash costs plus estimated corporate G&A, sustaining capital and closure costs
4. Gold Equivalent (AuEq) calculated via the formula: Au (g/t) + [Ag (g/t) / 82.8]
Skeena's CEO, Walter Coles commented, 'Eskay Creek was a remarkable discovery that became an extraordinary underground mine in 1994 and produced until 2008. This PEA demonstrates that Eskay Creek still has a bright future ahead, revitalized as an open-pit gold and silver mine, with the additional possibility for underground mining. The Project has the potential to produce an average of 306,000 gold-equivalent ounces per year with a diluted mill feed grade of 4.17 grams per tonne gold-equivalent. Also, as a brownfield site, Eskay Creek benefits from tremendous infrastructure installed by the previous operators. Finally, by creating a gold concentrate rather than doré, we are able to keep initial capital costs very low, at US$233 million, relative to the amount of precious metals produced; this also simplifies and reduces technical risks for the Project.'
PEA Overview
The 2019 Eskay Creek PEA considers an open-pit mine with on-site treatment of the mined material by conventional milling and flotation to recover a gold-silver concentrate for provision to third-party smelters. The mine will be an owner-operated, standard truck and shovel open-pit, with a leased mining fleet. At present, no contributions from previously reported underground resources are incorporated into this study. The processing capacity of 6,850 tonnes per day will result in a production lifespan of 8.6 years. An additional 1.5 years of pre-stripping, stockpiling and mine access development is planned prior to the processing facility becoming fully operational in Year 1. The PEA leverages Eskay Creek's extensive existing infrastructure, including all-weather access roads, previously permitted tailing storage facilities (TSF) and proximity to the recently commissioned 195 MW hydroelectric facilities and linked power grid.
The PEA is derived from the Company's pit-constrained resource estimate (February 28, 2019), and does not include results from the recently initiated and ongoing 2019 Phase I infill drilling program. The effective date of the PEA is November 7, 2019 and a technical report will be filed on the Company's website and SEDAR within 45 days of this disclosure.
Mineral resources are not mineral reserves and do not have demonstrated economic viability. The PEA is preliminary in nature and includes inferred mineral resources that are too speculative to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that PEA results will be realized.
Table 1: 2019 Eskay Creek 2019 PEA Detailed Parameters and Outputs
Assumptions | |
Gold Price (US$) | $1,325 |
Silver Price (US$) | $16 |
Exchange Rate (US$/C$) | 0.77 |
Discount Rate | 5% |
Royalties | 1% |
Contained Metals | |
Contained Gold Ounces (koz) | 2,212 |
Contained Silver Ounces (koz) | 53,404 |
Contained AuEq Ounces (koz) | 2,857 |
Mining | |
Mine Life (Years) | 8.6 |
Strip Ratio (Waste:Mineralization) | 7.2:1 |
Total Tonnage Mined (t) | 175,270 |
Total Mineralized Material Mined (t) | 21,307 |
Processing | |
Processing Throughput (TPD) | 6,850 |
Average Diluted Gold Grade (g/t) | 3.23 |
Average Diluted Silver Grade (g/t) | 78 |
Average Diluted Gold Equivalent Grade (g/t) | 4.17 |
Production | |
Gold Recovery | 91.1% |
Silver Recovery | 92.4% |
LOM Gold Production (koz) | 2,022 |
LOM Silver Production (koz) | 49,872 |
LOM Gold Equivalent Production (koz) | 2,624 |
LOM Average Annual Gold Production (koz) | 236 |
LOM Average Annual Silver Production (koz) | 5,812 |
LOM Average Annual Gold Equivalent Production (koz) | 306 |
Operating Costs | |
Mining Cost (C$/t Mined) | $3.44 |
Mining Cost (C$/t Milled) | $26.32 |
Processing Cost (C$/t Milled) | $21.64 |
G&A Cost (C$/t Milled) | $6.06 |
Total Operating Cost (C$/t Milled) | $54.03 |
Cash Costs and AISC | |
LOM Cash Cost (US$/oz Au) Net of Silver By-Product | $582 |
LOM Cash Cost (US$/oz AuEq) Co-Product | $731 |
LOM AISC (US$/oz Au) Net of Silver By-Product | $615 |
LOM AISC (US$/oz AuEq) Co-Product | $757 |
Capital Expenditures | |
Pre-Production Capital Expenditures (C$M) | $303 |
Sustaining Capital Expenditures (C$M) | $27 |
Reclamation Cost (C$M) | $52 |
Economics | |
After-Tax NPV (5%) (C$M) | $638 |
After-Tax IRR | 51% |
After-Tax Payback Period (Years) | 1.2 |
After-Tax NPV:CAPEX Ratio | 2.1:1 |
Pre-Tax NPV (5%) (C$M) | $993 |
Pre-Tax IRR | 63% |
Pre-Tax Payback Period (Years) | 1.1 |
Pre-Tax NPV:CAPEX Ratio | 3.3:1 |
Average Annual After-Tax Free Cash Flow (Year 1-9) (C$M) | $147 |
LOM After-Tax Free Cash Flow (C$M) | $959 |
1. Cash costs are inclusive of mining costs, processing costs, site G&A, treatment and refining charges and royalties
2. AISC includes cash costs plus corporate G&A, sustaining capital and closure costs
3. Gold Equivalent (AuEq) calculated via the formula: Au (g/t) + [Ag (g/t) / 82.8]
Sensitivities
After-tax economic sensitivities to commodity prices are presented in Table 2 illustrating the effects of varying gold and silver prices as compared to the base-case. Additional Project sensitivities will be presented in the Technical Report.
Table 2: After-Tax NPV (5%) and IRR Sensitivities to Commodity Prices
Lower Case | Base Case | Higher Case | |
Gold Price (US$/oz) | $1,200 | $1,325 | $1,500 |
Silver Price (US$/oz) | $14 | $16 | $18 |
After-Tax NPV (5%) (C$M) | $453 | $638 | $878 |
After-Tax IRR (%) | 40% | 51% | 63% |
After-Tax Payback (Years) | 1.6 | 1.2 | 0.9 |
Average Annual After-Tax Free Cash Flow (Years 1-9) (C$M) | $117 | $147 | $187 |
Eskay Creek Mineral Resource Estimate
The Company's current Mineral Resource Estimate (MRE; effective date of February 28, 2019) completed by SRK Consulting (Canada) forms the basis for this PEA. The MRE does not include drilling results from the Company's recently initiated and ongoing 2019 Phase I infill program.
Table 3: Pit constrained Mineral Resource Statement reported at 0.7 g/t AuEq cut-off:
| Grade | Contained Ounces | |||||
| Tonnes | AuEq | Au | Ag | AuEq | Au | Ag |
| (000) | g/t | g/t | g/t | oz (000) | oz (000) | oz (000) |
Total Indicated | 12,650 | 5.8 | 4.3 | 110 | 2,340 | 1,740 | 44,660 |
Total Inferred | 14,420 | 2.9 | 2.3 | 47 | 1,340 | 1,050 | 21,720 |
Table 4: Underground Mineral Resource Statement reported at a 5.0 g/t AuEq cut-off:
| Grade | Contained Ounces | |||||
| Tonnes | AuEq | Au | Ag | AuEq | Au | Ag
Shares
Watch latest videosSubscribe and FollowGet a daily dose of Los Angeles Herald news through our daily email, its complimentary and keeps you fully up to date with world and business news as well. News RELEASESPublish news of your business, community or sports group, personnel appointments, major event and more by submitting a news release to Los Angeles Herald. More Information
null in null
InternationalSectionTragedy in Spain: Diogo Jota and his brother die in car accidentMADRID, Spain: Liverpool footballer Diogo Jota and his younger brother, André Silva, have died in a car accident in Spain. Spanish... Early heatwave grips Europe, leaving 8 dead and nations on alertLONDON, U.K.: An unrelenting heatwave sweeping across Europe has pushed early summer temperatures to historic highs, triggering deadly... U.S. military, China, Russia in Space racePresident Donald Trump's plans to build a space-based Golden Dome missile defense shield have drawn immediate criticism from China,... Trump wins $16 million settlement from Paramount over CBS Harris editNEW YORK CITY, New York: Paramount has agreed to pay US$16 million to settle a lawsuit brought by U.S. President Donald Trump over... British PM faces major party revolt over welfare reformsLONDON, U.K.: British Prime Minister Keir Starmer won a vote in Parliament this week to move ahead with changes to the country's welfare... White House meeting between Trump, Netanyahu on July 7WASHINGTON, D.C.: President Donald Trump will meet Israeli Prime Minister Benjamin Netanyahu at the White House on Monday. President... CaliforniaSectionNvidia briefly tops Apple’s record in AI-fueled stock rallySANTA CLARA, California: Nvidia came within a whisker of making financial history on July 3, briefly surpassing Apple's all-time market... ICE raids leave crops rotting in California, farmers fear collapseSACRAMENTO, California: California's multibillion-dollar farms are facing a growing crisis—not from drought or pests, but from a sudden... Grammarly acquires Superhuman to boost AI workplace toolsSAN FRANCISCO, California: Grammarly is doubling down on AI-powered productivity tools with the acquisition of Superhuman, a sleek... Robinhood launches stock tokens for EU investors, adds OpenAIMENLO PARK, California: Robinhood is giving European investors a new way to tap into America's most prominent tech names — without... Trump hints at DOGE investigation of Musk subsidiesWASHINGTON, DC - U.S. President Donald Trump on Tuesday claimed Elon Musk's success has been built on government subsidies. Without... Nvidia execs sell $1 billion in stock as AI boom drives record pricesSANTA CLARA, California: Executives at Nvidia have quietly been cashing in on the AI frenzy. According to a report by the Financial... Movie Review |